Work Performed, July 24th to July 28th 
Roadway Improvement, paving:
·         Fredric Court
·         Glenway Drive
·         Porter Court cul-de-sac
·         Astor Court
·         Indian Ridge Drive, patches only
·         Myrtle Parkway
·         Russet Way, patches only

Work Anticipated to be Performed, July 31st through Mid-August
Roadway Improvements, pavement removal and paving new asphalt surface:
·         Concord Lane
·         Avalon Court
·         Combria Court
·         Pfingsten Road
·         Rugen Road
·         Springdale Avenue
·         Bette Lane
·         Rolling Pass
·         Sheryl Lane
·         Somerset Drive
·         Oxford Lane
·         Beech Drive
·         Various small patching throughout the Village.

Underground Utility Improvements
·         Kendale Avenue

Concrete curb & gutter replacement:
·         Kendale Avenue
·         Beech Drive

Due to unexpected delays, the project is taking longer than anticipated.  The Village has received a commitment from the contractor the roadway improvements (pavement removal and surface paving) will begin during the middle of next week.  Once the contractor arrives in the Village, they will remain here until the work is completed.  We are hopeful the work will be completed by mid-August.

Thanks again for all your patience and understanding as you have been traveling and living along streets with construction.