Storm sewer and underground utility improvements:
·
Structure adjustments along entire project
·
Storm sewer installation along Rugen Road
Concrete curb & gutter and sidewalk replacements along:
·
Keenan Drive, north side of the street
·
Concord Lane, north side of the street
·
Avalon Court, west side of street
·
Sheryl Lane
·
Somerset Drive, east side of the street
·
Oxford Lane cul-de-sac
·
Bette Lane, east side of street
·
Springdale Avenue, south side of street
·
Rugen Road, east side of street
·
Rollling Pass, west side of street
·
Pfingsten Road
Asphalt driveway restoration along:
·
Keenan Drive
·
Rolling Pass
Work Anticipated to be Performed, June 26th to
June 30th
·
No work scheduled to be performed on Monday,
July 3rd or Tuesday, July 4th on-site
The Village will provide all notices regarding driveway
restrictions during concrete curb & gutter and sidewalk replacements.
Please be on the look-out for these notices.
Asphalt resurfacing of roadways is anticipated to begin the week of July 10th.
Construction
will not be delayed due to the current shut-down of IDOT projects.
Have a
safe and enjoyable July 4th Weekend.