Work Performed, June 26th to June 30th  
Storm sewer and underground utility improvements:
·         Structure adjustments along entire project
·         Storm sewer installation along Rugen Road

Concrete curb & gutter and sidewalk replacements along:
·         Keenan Drive, north side of the street
·         Concord Lane, north side of the street
·         Avalon Court, west side of street
·         Sheryl Lane
·         Somerset Drive, east side of the street
·         Oxford Lane cul-de-sac
·         Bette Lane, east side of street
·         Springdale Avenue, south side of street
·         Rugen Road, east side of street
·         Rollling Pass, west side of street
·         Pfingsten Road

Asphalt driveway restoration along:
·         Keenan Drive
·         Rolling Pass

Work Anticipated to be Performed, June 26th to June 30th  
·         No work scheduled to be performed on Monday, July 3rd or Tuesday, July 4th on-site

The Village will provide all notices regarding driveway restrictions during concrete curb & gutter and sidewalk replacements. Please be on the look-out for these notices.

Asphalt resurfacing of roadways is anticipated to begin the week of July 10th.

Construction will not be delayed due to the current shut-down of IDOT projects.

 