Friday, September 1, 2017

Landscape Restoration to Begin Soon

Landscape restoration of those areas disturbed during construction is scheduled to begin within the next two weeks.  Areas that will be restored include:

The Village is committed to getting the work 100% completed, include landscape restoration as quickly as possible. Unfortunately, due to some circumstances out of our control, the work was delayed. We believe the issues have been resolved and work will begin soon.

Thanks again for all your patience and understanding.

Friday, August 18, 2017

Major Construction Completed

Work Performed, August 14th to August 18th
Roadway Improvements, paving new asphalt surface:
·         Oxford Lane
·         Somerset Drive
·         Brook Lane
·         Beech Drive
·         Ferndale Road
·         Kittyhawk Lane
·         Pinehurst Drive
·         The Glen Metra Parking Lot, surface patches only
·         Kendale Drive, patching only
·         Bonnie Glen, patching only

Miscellaneous other tasks including:
·         Asphalt driveway restorations
·         Repaired previously damaged curb
·         General site clean-up

Work Anticipated to be Performed to Complete project
·         Landscape restorations
o   Areas with storm sewer improvements, topsoil and sod
o   Areas with curb and sidewalk repairs, topsoil and seed
·         Pavement markings
·         Pick-up barricades around jobsites
·         General site clean-up

The major construction operations of the project are now completed. All roadways are paved with limited work remaining to be completed.

Landscape restorations will be completed in the coming weeks.  In areas where concrete curb & gutter or sidewalk was replaced, the landscape will be restored with topsoil and seed. In areas of underground utility improvements (primarily storm sewer), the landscape will be restored with topsoil and sod. These areas will have topsoil installed and graded; however, sod will not be installed until mid-September when growing conditions are typically more favorable.

Due to limited work remaining, this will be the final blog post for the project. We hope you found the information provided helpful. If you have any questions or concerns, please contact the Village Project Manager, Adriana Webb, at 847-904-4414.

Thanks again for all your patience and hopefully you are satisfied with the work that was performed and are enjoying the new streets.

Thursday, August 10, 2017

Significant Roadway Work On-Going.

Work Performed, August 1st to August 11th
Roadway Improvement, pavement removal and paving new asphalt surface
·         Rolling Pass
·         Lindenwood Lane
·         Crestwood Lane, surface patching only
·         Kittyhawk Lane, surface patching only
·         Concord Lane
·         Avalon Court
·         Cambria Court
·         Pfingsten Road
·         Rugen Road
·         Springdale Avenue
·         Bette Lane
·         Sheryl Lane
·         Countryside Lane, surface patching only
·         Glenview Road, surface patching only
·         Pinehurst Street, surface patching only
·         Downtown Metra Commuter Lot along Depot Street, surface patching only

Roadway Improvements, pavement removal:
·         Oxford Lane
·         Somerset Drive
·         Beech Drive
·         Ferndale Road

Concrete curb & gutter replacement:
·         Kendale Drive
·         Bonnie Glen Lane
·         Beech Drive

Storm Sewer Improvements:
·         Castle Drive / Knollwood Drive
·         Bonnie Glen Lane
·         Kendale Drive
·         Rugen Road, structure adjustments
·         Oxford Lane, structure adjustments only
·         Somerset Drive, structure adjustments only
·         Underground utility / storm sewer improvements anticipated to be completed by end of the week.

 
Work Anticipated to be Performed, August 14th to August 18th  

Roadway Improvements, paving new asphalt surface:
·         Oxford Lane
·         Somerset Drive
·         Beech Drive
·         Ferndale Road
·         All areas with asphalt surface previously removed scheduled to be paved by Tuesday, August 15th.

Roadway Improvements, pavement removal and new asphalt pavement
·         The Glen Metra Parking Lot, surface patches only

There has been significant activity over the past two weeks on many of the streets within the roadway improvement project. We are anticipating a majority of the work will be completed by the end of next week. 

Once the paving work is completed, landscape restoration and overall site clean-up will be performed.

Thanks again for all your patience during the construction operations and hopefully you are enjoying your new street!!!

Saturday, July 29, 2017

Roadway Improvements to Resume Next Week.

Work Performed, July 24th to July 28th 
Roadway Improvement, paving:
·         Fredric Court
·         Glenway Drive
·         Porter Court cul-de-sac
·         Astor Court
·         Indian Ridge Drive, patches only
·         Myrtle Parkway
·         Russet Way, patches only

Work Anticipated to be Performed, July 31st through Mid-August
Roadway Improvements, pavement removal and paving new asphalt surface:
·         Concord Lane
·         Avalon Court
·         Combria Court
·         Pfingsten Road
·         Rugen Road
·         Springdale Avenue
·         Bette Lane
·         Rolling Pass
·         Sheryl Lane
·         Somerset Drive
·         Oxford Lane
·         Beech Drive
·         Various small patching throughout the Village.

Underground Utility Improvements
·         Kendale Avenue

Concrete curb & gutter replacement:
·         Kendale Avenue
·         Beech Drive

Due to unexpected delays, the project is taking longer than anticipated.  The Village has received a commitment from the contractor the roadway improvements (pavement removal and surface paving) will begin during the middle of next week.  Once the contractor arrives in the Village, they will remain here until the work is completed.  We are hopeful the work will be completed by mid-August.

Thanks again for all your patience and understanding as you have been traveling and living along streets with construction.

 

Friday, July 21, 2017

Pavement Removal and Paving Continues

Work Performed, July 17th to July 21st    
Storm sewer and underground utility improvements:
·         Beech Drive
·         Sheryl Lane

Roadway Improvement, pavement removal:
·         Maple Leaf Drive, patches only
·         Astor Court
·         Porter Court cul-de-sac
·         Fredric Court
·         Myrtle Parkway
·         Glenway Drive
·         Indian Ridge Drive, patches only
·         Russet Way, patches only

Roadway Improvement, paving:
·         Keenan Lane
·         Halina Drive
·         Maple Leaf Drive

Asphalt patching and driveway restoration along:
·         Rugen Road
·         Springdale Avenue
·         Avalon Court
·         Myrtle Parkway
·         Somerset Drive
·         Oxford Lane
·         Glenway Drive

Work Anticipated to be Performed, July 24th to July 28th  
Roadway Improvement, paving:
·         Astor Court
·         Porter Court cul-de-sac
·         Fredric Court
·         Myrtle Parkway
·         Glenway Drive
·         Indian Ridge Drive, patches only
·         Russet Way, patches only

Due to the weather and equipment break-downs, the roadway improvements were delayed with paving starting on Friday. It is anticipated all areas with pavement previously removed will be paved by the end of next week.

Thanks again for all your understanding during these unforeseen circumstances and weather delays.

Friday, July 14, 2017

Asphalt Surface Removal Started. Paving to Begin

Work Performed, July 10th to July 14th   
Storm sewer and underground utility improvements:
·         Beech Drive
·         Sheryl Lane

Concrete curb & gutter and sidewalk replacements along:
·         Avalon Court, east side of the street
·         Somerset Drive, west side of the street
·         Oxford Lane cul-de-sac
·         Bette Lane, west side of street
·         Springdale Avenue, north side of street
·         Rugen Road, west side of street

Roadway Improvement, pavement removal:
·         Keenan Lane
·         Halina Drive
·         Various patching areas on the west side of the Village.
 

Work Anticipated to be Performed, July 17th to July 21st
Storm sewer and underground utility improvements
·         Structure adjustments to be completed around project sites
·         Complete storm sewer along Beech Drive
·         Kendale Drive
·         Bonnie Glen Lane
·         Knollwood Lane

Asphalt patching and driveway restorations along:
·         Rugen Road
·         Somerset Drive
·         Oxford Lane
·         Avalon Court 

Roadway Improvements, pavement removal to continue along:
·         Astor Court
·         Various patching locations on the west side of the Village.

 Roadway Improvements, new asphalt pavement anticipated to start on Wednesday along:
·         Keenen Lane
·         Halina Drive
·         Astor Court
·         Various patching locations on the west side of the Village.

Due to the weather and equipment break-downs, the roadway improvements were delayed in starting from Wednesday to Friday. 

Thanks again for all your patience as you live on and around streets with construction on-going.

Saturday, July 1, 2017

Concrete Work On-Going

Work Performed, June 26th to June 30th  
Storm sewer and underground utility improvements:
·         Structure adjustments along entire project
·         Storm sewer installation along Rugen Road

Concrete curb & gutter and sidewalk replacements along:
·         Keenan Drive, north side of the street
·         Concord Lane, north side of the street
·         Avalon Court, west side of street
·         Sheryl Lane
·         Somerset Drive, east side of the street
·         Oxford Lane cul-de-sac
·         Bette Lane, east side of street
·         Springdale Avenue, south side of street
·         Rugen Road, east side of street
·         Rollling Pass, west side of street
·         Pfingsten Road

Asphalt driveway restoration along:
·         Keenan Drive
·         Rolling Pass

Work Anticipated to be Performed, June 26th to June 30th  
·         No work scheduled to be performed on Monday, July 3rd or Tuesday, July 4th on-site

The Village will provide all notices regarding driveway restrictions during concrete curb & gutter and sidewalk replacements. Please be on the look-out for these notices.

Asphalt resurfacing of roadways is anticipated to begin the week of July 10th.

Construction will not be delayed due to the current shut-down of IDOT projects.

 

Have a safe and enjoyable July 4th Weekend.