Friday, July 21, 2017

Pavement Removal and Paving Continues

Work Performed, July 17th to July 21st    
Storm sewer and underground utility improvements:
·         Beech Drive
·         Sheryl Lane

Roadway Improvement, pavement removal:
·         Maple Leaf Drive, patches only
·         Astor Court
·         Porter Court cul-de-sac
·         Fredric Court
·         Myrtle Parkway
·         Glenway Drive
·         Indian Ridge Drive, patches only
·         Russet Way, patches only

Roadway Improvement, paving:
·         Keenan Lane
·         Halina Drive
·         Maple Leaf Drive

Asphalt patching and driveway restoration along:
·         Rugen Road
·         Springdale Avenue
·         Avalon Court
·         Myrtle Parkway
·         Somerset Drive
·         Oxford Lane
·         Glenway Drive

Work Anticipated to be Performed, July 24th to July 28th  
Roadway Improvement, paving:
·         Astor Court
·         Porter Court cul-de-sac
·         Fredric Court
·         Myrtle Parkway
·         Glenway Drive
·         Indian Ridge Drive, patches only
·         Russet Way, patches only

Due to the weather and equipment break-downs, the roadway improvements were delayed with paving starting on Friday. It is anticipated all areas with pavement previously removed will be paved by the end of next week.

Thanks again for all your understanding during these unforeseen circumstances and weather delays.

Friday, July 14, 2017

Asphalt Surface Removal Started. Paving to Begin

Work Performed, July 10th to July 14th   
Storm sewer and underground utility improvements:
·         Beech Drive
·         Sheryl Lane

Concrete curb & gutter and sidewalk replacements along:
·         Avalon Court, east side of the street
·         Somerset Drive, west side of the street
·         Oxford Lane cul-de-sac
·         Bette Lane, west side of street
·         Springdale Avenue, north side of street
·         Rugen Road, west side of street

Roadway Improvement, pavement removal:
·         Keenan Lane
·         Halina Drive
·         Various patching areas on the west side of the Village.
 

Work Anticipated to be Performed, July 17th to July 21st
Storm sewer and underground utility improvements
·         Structure adjustments to be completed around project sites
·         Complete storm sewer along Beech Drive
·         Kendale Drive
·         Bonnie Glen Lane
·         Knollwood Lane

Asphalt patching and driveway restorations along:
·         Rugen Road
·         Somerset Drive
·         Oxford Lane
·         Avalon Court 

Roadway Improvements, pavement removal to continue along:
·         Astor Court
·         Various patching locations on the west side of the Village.

 Roadway Improvements, new asphalt pavement anticipated to start on Wednesday along:
·         Keenen Lane
·         Halina Drive
·         Astor Court
·         Various patching locations on the west side of the Village.

Due to the weather and equipment break-downs, the roadway improvements were delayed in starting from Wednesday to Friday. 

Thanks again for all your patience as you live on and around streets with construction on-going.

Saturday, July 1, 2017

Concrete Work On-Going

Work Performed, June 26th to June 30th  
Storm sewer and underground utility improvements:
·         Structure adjustments along entire project
·         Storm sewer installation along Rugen Road

Concrete curb & gutter and sidewalk replacements along:
·         Keenan Drive, north side of the street
·         Concord Lane, north side of the street
·         Avalon Court, west side of street
·         Sheryl Lane
·         Somerset Drive, east side of the street
·         Oxford Lane cul-de-sac
·         Bette Lane, east side of street
·         Springdale Avenue, south side of street
·         Rugen Road, east side of street
·         Rollling Pass, west side of street
·         Pfingsten Road

Asphalt driveway restoration along:
·         Keenan Drive
·         Rolling Pass

Work Anticipated to be Performed, June 26th to June 30th  
·         No work scheduled to be performed on Monday, July 3rd or Tuesday, July 4th on-site

The Village will provide all notices regarding driveway restrictions during concrete curb & gutter and sidewalk replacements. Please be on the look-out for these notices.

Asphalt resurfacing of roadways is anticipated to begin the week of July 10th.

Construction will not be delayed due to the current shut-down of IDOT projects.

 

Have a safe and enjoyable July 4th Weekend.

Friday, June 23, 2017

Concrete Replacements On-Going

Work Performed, June 19th to June 23rd  
Storm sewer and underground utility improvements along:
·         Rugen Road
·         Bette Lane
·         Springdale Avenue 

Concrete Curb & Gutter and Sidewalk Replacements along:
·         Keenan Drive, south side of the street only
·         Halina Drive
·         Concord Lane, portions of the south side of the street only.
·         Cambria Court
·         Astor Court
·         Myrtle Parkway
·         Pfingsten Road
·         Rolling Pass
·         Somerset Drive
·         Oxford Lane
·         Sheryl Lane

Work Anticipated to be Performed, June 26th to June 30th  
Storm sewer and underground utility improvements:
·         Structure adjustments along entire project

Concrete curb & gutter and sidewalk replacements along:
·         Keenan Drive, north side of the street
·         Concord Lane, selected areas within neighborhood
·         Rolling Pass, west side of the street
·         Rugen Road, east side of the street
·         Springdale Avenue
·         Bette Lane 

The Village will provide all notices regarding driveway restrictions during concrete curb & gutter and sidewalk replacements. Please be on the look-out for these notices.

It is anticipated all concrete curb & gutter and sidewalk that has been or will be removed will be poured by the end of the week and prior to the July 4th weekend.  Also, all residents will have access to their driveway no later than Saturday, July 1st for the holiday weekend.

Following the July 4th weekend, the remaining concrete work will be completed and roadway resurfacing will begin.

Thanks again for all your patience and understanding during the construction process.

Monday, June 19, 2017

Storm Sewer Work Continues. Concrete Curb and Gutter Replacement Starting

Work Performed, June 12th to June 16th
Storm sewer and underground utility improvements along:
·         Somerset Drive
·         Oxford Lane
·         Pfingsten Road, south of East Lake Avenue

Work Anticipated to be Performed, June 19th to June 23rd
Storm sewer and underground utility improvements along:
·         Rugen Road
·         Bette Lane
·         Springdale Avenue 

Concrete Curb & Gutter and Sidewalk Replacements along:
·         Keenan Drive, south side of the street only
·         Halina Drive
·         Concord Lane, portions of the south side of the street only.
·         Cambria Court
·         Astor Court
·         Myrtle Parkway

The Village will provide all notices regarding driveway restrictions during concrete curb & gutter and sidewalk replacements. There has been significant confusion due to the contractor providing a separate notice. We apologize for this confusion and are working with the contractor to ensure it does not happen in the future.

Thanks again for all your patience and understanding during the construction process.

Tuesday, June 13, 2017

Underground Storm Improvements On-Going. Concrete Curb and Gutter Replacement Started

Work Completed, June 5th to June 9th  
Underground storm sewer repair work and drainage structure replacement along:
·         Keenan Lane
·         Halina Drive
·         Rolling Pass
·         Pfingsten Road
·         Somerset Drive
·         Oxford Lane

Preparation for concrete curb & gutter replacement along:
·         Keenan Lane (north side)
·         Halina Drive
·         Rolling Pass
·         Pfingsten Road

Work Anticipated to be performed, June 19th to June 23rd  
Concrete curb & gutter replacement along the following streets:
·         Keenan Lane (South Side)
·         Halina Drive
·         Pfingsten Road

Some work will be performed in front of driveways. If work is scheduled to be performed in front of your driveway, access will be restricted for approximately 5 days. The Village of Glenview will hand-deliver a letter to your door prior to removing the curb & gutter and/or sidewalk in front of your driveway stating the day and time in which the vehicles should be removed and parking instructions. Please be on the look-out for these letters. Everything will be done to minimize the amount of time access is restricted.

Thank you again for all your patience during construction.

Friday, May 26, 2017

1st Round of Minor of Resurfacing Completed. Storm Sewer work to Begin Week of June 5th

Work Completed Last Week, May 22nd to May 26th
Resurfacing and minor asphalt patching along the following streets:
·         Central Parkway
·         Woodlawn Avenue
·         Pleasant Lane
·         Fontana Drive
·         Flora Avenue
·         George Court
·         Robincrest Lane
·         Fir Street

Work Anticipated to be next week, May 30th to June 2nd
Village staff will continue to mark-out locations for storm sewer improvements, concrete curb & gutter repair, sidewalk repair, and street patching along:
·         Rolling Pass – Glenview Road to Northern Cul-de-Sac
·         Keenan Lane – Pfingsten Road to East End
·         Halina Drive – Keenan Lane to North End

Work Anticipated week of June 5th
·         Storm sewer and other underground utility improvements along:
o   Rolling Pass
o   Keenan Lane
o   Halina Drive 

As work is anticipated along various streets within the Village of Glenview, residents will be notified regarding timing of work, road closures, and restrictions to driveway access.

Thanks again for all your patience.

 

Have a safe and enjoyable Memorial Day Weekend!!!