Friday, June 23, 2017

Concrete Replacements On-Going

Work Performed, June 19th to June 23rd  
Storm sewer and underground utility improvements along:
·         Rugen Road
·         Bette Lane
·         Springdale Avenue 

Concrete Curb & Gutter and Sidewalk Replacements along:
·         Keenan Drive, south side of the street only
·         Halina Drive
·         Concord Lane, portions of the south side of the street only.
·         Cambria Court
·         Astor Court
·         Myrtle Parkway
·         Pfingsten Road
·         Rolling Pass
·         Somerset Drive
·         Oxford Lane
·         Sheryl Lane

Work Anticipated to be Performed, June 26th to June 30th  
Storm sewer and underground utility improvements:
·         Structure adjustments along entire project

Concrete curb & gutter and sidewalk replacements along:
·         Keenan Drive, north side of the street
·         Concord Lane, selected areas within neighborhood
·         Rolling Pass, west side of the street
·         Rugen Road, east side of the street
·         Springdale Avenue
·         Bette Lane 

The Village will provide all notices regarding driveway restrictions during concrete curb & gutter and sidewalk replacements. Please be on the look-out for these notices.

It is anticipated all concrete curb & gutter and sidewalk that has been or will be removed will be poured by the end of the week and prior to the July 4th weekend.  Also, all residents will have access to their driveway no later than Saturday, July 1st for the holiday weekend.

Following the July 4th weekend, the remaining concrete work will be completed and roadway resurfacing will begin.

Thanks again for all your patience and understanding during the construction process.