Friday, July 21, 2017

Pavement Removal and Paving Continues

Work Performed, July 17th to July 21st    
Storm sewer and underground utility improvements:
·         Beech Drive
·         Sheryl Lane

Roadway Improvement, pavement removal:
·         Maple Leaf Drive, patches only
·         Astor Court
·         Porter Court cul-de-sac
·         Fredric Court
·         Myrtle Parkway
·         Glenway Drive
·         Indian Ridge Drive, patches only
·         Russet Way, patches only

Roadway Improvement, paving:
·         Keenan Lane
·         Halina Drive
·         Maple Leaf Drive

Asphalt patching and driveway restoration along:
·         Rugen Road
·         Springdale Avenue
·         Avalon Court
·         Myrtle Parkway
·         Somerset Drive
·         Oxford Lane
·         Glenway Drive

Work Anticipated to be Performed, July 24th to July 28th  
Roadway Improvement, paving:
·         Astor Court
·         Porter Court cul-de-sac
·         Fredric Court
·         Myrtle Parkway
·         Glenway Drive
·         Indian Ridge Drive, patches only
·         Russet Way, patches only

Due to the weather and equipment break-downs, the roadway improvements were delayed with paving starting on Friday. It is anticipated all areas with pavement previously removed will be paved by the end of next week.

Thanks again for all your understanding during these unforeseen circumstances and weather delays.