Friday, May 26, 2017

1st Round of Minor of Resurfacing Completed. Storm Sewer work to Begin Week of June 5th

Work Completed Last Week, May 22nd to May 26th
Resurfacing and minor asphalt patching along the following streets:
·         Central Parkway
·         Woodlawn Avenue
·         Pleasant Lane
·         Fontana Drive
·         Flora Avenue
·         George Court
·         Robincrest Lane
·         Fir Street

Work Anticipated to be next week, May 30th to June 2nd
Village staff will continue to mark-out locations for storm sewer improvements, concrete curb & gutter repair, sidewalk repair, and street patching along:
·         Rolling Pass – Glenview Road to Northern Cul-de-Sac
·         Keenan Lane – Pfingsten Road to East End
·         Halina Drive – Keenan Lane to North End

Work Anticipated week of June 5th
·         Storm sewer and other underground utility improvements along:
o   Rolling Pass
o   Keenan Lane
o   Halina Drive 

As work is anticipated along various streets within the Village of Glenview, residents will be notified regarding timing of work, road closures, and restrictions to driveway access.

Thanks again for all your patience.

 

Have a safe and enjoyable Memorial Day Weekend!!!